Projects
This Common Effluent Treatment Plant for treatment of effluents generated by industrial units in Patalganga MIDC industrial area was conceived as a joint effort between Maharashtra Industrial Development Corporation, Patalganga and Rasayani Industries Association and Maharashtra Pollution Control Board.
It was decided to set up a public limited company for implementation of the CETP. Hydroair Tectonics (PCD) Pvt. Ltd. was selected as a Joint Venture Partner and a Joint Venture company named PRIA CETP (I) Ltd. was formed for implementation of this project. The project was completed through active cooperation from officials of MPCB & MIDC.
|
Overall
View Of Waste Water Treatment Plant |
Technical Features
- Scheme approved by IIT, Mumbai.
- Additional benefit of generation of biogas which will be used to generate power and thus reduce the power consumption.
- Plants working on conventional technology would require 620 KBA power.
- Higher loading rates due to anaerobic system and thus smaller unit sizes leading to saving in capital cost.
- Sludge handling by mechanical means : Filter press, Dewatered sludge will be stored temporarily and transported to Government approved designated site.
- Minimal chemical consumption.
- In tune with present Government policy of sustainable development and not limited to meeting discharge standards.
Treatment Philosophy
PRIMARY TREATMENT |
: |
Equalisation
Neutralisation.
Flash mixing for chemical dosing Clariflocculation |
SECONDARY TREATMENT |
: |
Anaerobic based on UASB (Upflow Anaerobic Sludge Blanket) process
Anaerobic polishing step with inbuilt
settling |
SLUDGE HANDLING |
: |
By mechanical means:Automatic Belt
Filter Press.
Dewatered sludge will be stored temporarily and transported to Government approved designed site |
| BIOTAS UTILISATION |
: |
By Dual Fuel Engine |
CETP AT GLANCE
LOCATION |
: |
Plot No. P 58, MIDC Industrial Area,
Patalganga, Dist. Raigad, Maharashtra |
| TREATMENT CAPACITY |
: |
15,000 m3/day |
| LAND |
: |
30,000 m2 |